How many dust wipes should be taken during a PCAD if no deleading work was performed?

Prepare for the Massachusetts Lead Inspector Test. Study with interactive questions, each with detailed explanations. Ace your exam!

During a Post-Construction Assessment of Deleading (PCAD), if no lead hazard reduction activities have been performed in the property, it is not required to take any dust wipes. The purpose of dust wipe sampling is typically to evaluate lead dust levels and ensure that any previous deleading efforts effectively reduced lead risks. Since no deleading work was conducted in this scenario, there is no need for sampling to assess lead dust contamination, and dust wipes would not provide meaningful data. Therefore, the correct approach would align with the understanding that if no work involving lead hazard reduction took place, no samples are needed.